Installation of New Cyclones.
Here we have H&W Engineers installing new Cyclones at a Dairy in mid Wales.
Prior to installing the new Cyclones we had to remove the redundant ones, we dis-connected the services and pipework, etc.
Crane the units out through the roof using a 160 ton crane and traversed to a marshaling area on site.
We delivered the new Cyclones to site, using the same crane to lift into position, install the pipework and re-connected the services and secured the units to the steelwork.