Installation of Cremator and Abatement Plant
H & W Lift and Shift have just completed the installation of a 22 ton Cremator and Abatement plant (flue's, chimney, heat exchanger) at a crematorium in Southern England, The Cremator and it's equipment was off loaded from incoming transport using a 200 ton crane with full ballast, and craned onto a platform erected by H & W engineers using railway sleepers and steel plates, the equipment was then skated into position with the aid of one of our 7 ton fork lift trucks.
The plant was then built up when in position (flue's, pipe work connected), secured, lined, levelled and services connected.