Collection, delivery and installation of 2 off 9 ton Boilers.
Using 2 of our rigid vehicles fitted with hi-ab type cranes we collected 2 x 9 boilers from a Company in the Midlands, delivered to a NHS Hospital in the North of Wales, once off loaded using our hi-ab type cranes the boilers we're skated into position, H & W Lift and Shift engineers then built the platforms around the boilers, connected the pipework, electrics, etc, lined, levelled and fastened down.